Peusangan 1and 2, Indonesia

Manufacturing of the turbine and generator components for the Peusangan 1 and 2 hydropower plants in Indonesia are at an advanced stage, with completion originally due by May 2016.

The contract for the electro-mechanical works at the hydropower plants was signed between PT PLN (Persero) and ANDRITZ HYDRO in August 2013.

Inlet valves during manufacturing

Inlet valves during manufacturing

Jointly financed by the Japan International Cooperation Agency (JICA) and the Government of Indonesia, Nippon Koei Co. Ltd of Japan is the consultant appointed to oversee the implementation of this hydropower project.

HPP Peusangan 1 consists of an underground powerhouse while Peusangan 2 has a surface powerhouse. Both are run-of-river power plants, located on the Peusangan River and adjacent to Lake Laut Tawar in the central region of Aceh Province in northwestern Sumatra.

ANDRITZ HYDRO’s scope of supply for HPP Peusangan 1 and HPP Peusangan 2 comprises vertical Francis turbines, generators, transformers, 150 kV switchyards, cranes, and comprehensive mechanical and electrical auxiliaries. The supply of turbines, generators, and the high voltage system is being executed by ANDRITZ HYDRO India, whereas the supply of the low voltage system, telecommunication, and control system, as well as local transportation and installation is done by ANDRITZ HYDRO Indonesia.

Initially the contractual period was 42 months. However, due to unforeseen geological issues the civil works are being delayed by 24 months. Consequently, the revised completion date for trial operation of the last unit is now April 2019.

HPP Peusangan 1 and 2 will be the first large hydropower plants in the region, with an expected annual output of 327 GWh of electrical energy. 

Stator assembly

Stator assembly

TECHNICAL DATA  

Peusangan 1: 
Output2 × 23.1 MW
2 × 26.5 MVA
Voltage11 kV
Head205.3 m
Speed600 rpm
Runner diameter1,200 mm
Peusangan 2: 
Output2 × 22 MW
2 × 25.3 MVA
Voltage11 kV
Head187.7 m
Spead600 rpm
Runner diameter1,200 mm

New projects

Site visit
Malawi - Nkula A

A contract to rehabilitate and upgrade the Nkula A hydropower station has been awarded to ANDRITZ HYDRO as leader to a consortium by the Millennium Challenge Account - Malawi (MCA-M).

Power house and Sholayar River
India - Sholayar

ANDRITZ HYDRO signed a contract for the renovation, moderni­za­tion, and upgrade of the Sholayar hydro­power plant, located on the Sholayar River in Tamil Nadu, India.

Powerhouse and existing penstock of HPP Carlos Fonseca
Nicaragua - Centroamérica and Carlos Fonseca

Nicaragua’s Government of Reconciliation and National Unity - through Empresa Nicaragüense de Electricidad (ENEL) - signed a contract with ANDRITZ HYDRO in October 2015 for the renovation of the hydroelectric stations Centroamérica and Carlos Fonseca.

Reine, Lofoten Islands, Norway - Copyright demerzel21/Fotolia
Norway - Smibelg and Storåvatn

SmiSto Kraft AS has awarded ANDRITZ HYDRO a contract for the delivery of the electro-mechanical equipment of the new Smibelg and Storåvatn hydroelectric power plants.

Manufacturing of stator for HPP Xekaman 1
Laos - Xekaman Xanxay

In July 2015, ANDRITZ HYDRO signed a contract with Song Da Corporation of Vietnam for the supply of the complete electro-mechanical equipment and technical services for the Xekaman Xanxay hydropower plant in Laos.

Downstream view of power house, dam and spillway
Brazil - HPP Foz do Areia

ANDRITZ HYDRO signed a contract for the modernization of their largest hydropower plant Foz do Areia on the Iguaçu River in the state of Paraná.

Lower Monumental Dam, USA
USA - Lower Monumental Dam

The U.S. Army Corps of Engineers, Walla Walla District, awarded a contract to ANDRITZ HYDRO in July 2015, for generator rewind and turbine cavitation repairs at HPP Lower Monumental Dam.

Dam and spillway
South Korea - Andong

K-water, a South Korean utility and top level water service company, has awarded ANDRITZ HYDRO an order for the refurbishment of the Andong hydropower station on the Nakdong River in South Korea.

Highlights

render 2
Italy - HPP Camaioni

In November 2015, ANDRITZ HYDRO received a contract for the supply of electro-mechanical equipment for the new Camaioni hydropower plant in Italy from HGE Srl, a private investor which has been active in the small hydro sector for many years.

HY-portalimage-loop1
USA - Olmsted

ANDRITZ HYDRO was contracted to provide two turbine-generator units, including auxiliary mechanical equipment and electrical controls, for the new Olmsted powerhouse.

Convento_Viejo
Nepal - Kabeli B1

At the end of 2015, ANDRITZ HYDRO received an order for the Kabeli B1 hydropower station from Arun Kabeli Power Limited.

20151022_181232
France - HPP St. Christophe, Reallon, Charmaix

In December 2015, ANDRITZ HYDRO successfully commissioned two Mini Compact hydropower plants in France: HPP Saint Christophe and HPP Real­lon.

hy-image-hydro
Norway - Ringdalen

ANDRITZ HYDRO to supply of the electro- and hydro-mechanical equipment for the Ringedalen hydropower plant in Norway.

Ecuador - HPP Due

ANDRITZ HYDRO was awarded a new contract for the supply of electro-mechanical equipment for the Due hydropower plant in 2015.

hy-image-hydro
Switzerland - Rhone Oberwald

ANDRITZ HYDRO to deliver the complete electro-mechanical equipment for the new HPP Rhone Oberwald in December 2015.

hy-image-hydro
Chile, Convento Viejo

Sociedad Concesionaria Embalse Convento Viejo S.A. has awarded ANDRITZ HYDRO a contract for the supply of electro-mechanical equipment for the new Convento Viejo hydropower plant.

Costa Rica - Los Negros II

ANDRITZ HYDRO won a contract for the supply of turbine equipment for the new Los Negros II hydropower plant.

DSC_01361
DR Congo, Koni

Koni hydropower station has a total installed capa­city of 42 MW and is equipped with three vertical Francis turbines.

IMG_2561
Mexico, La Venta

During tropical storm Manuel, the hydropower plant was flooded and the radial gates, automation, and electrical equipment were destroyed.

hy-image-hydro
Turkey, Yusufeli Barajı ve HES İnşaatı

ANDRITZ HYDRO to supply electro-mechanical equipment for the Yusufeli Dam and hydroelectric power plant.

DSC_0864
New Zealand, Aratiatia

ANDRITZ HYDRO to refurbish the Aratiatia hydropower station on the river Waikato on the North Island.

China, Da A Guo

Supply of electro-mechanical equipment for HPP Da A Guo, located downstream of HuoQu River, 600 km west of the city of Chengdu in Sichuan Province, PR China.

IMG_0870
Austria, Kaunertal

Order for the renewal of the existing penstock at the 395 MW Kaunertal hydropower plant, located in western Austria in the state of Tyrol.

Next article

Carlos Lleras Restrepo, Colombia

Read more

List of all articles

Content of HYDRO News 29

Read more
Contact us
HYDRO News Editorial Office
Eibesbrunnergasse 20
1120 Vienna
Downloads
  • hy-hn29-en.pdf
    HYDRO NEWS Issue 29 PDF : 8.4 MB
  • Article as PDF PDF : 811 KB